The PASC Lodge Addition - Pictures from August 6th

More demolition



The old front comes off
That's Troy, I think,
removing the last of the
upper deck (correct me
if I'm wrong Gordon)
Here's one from Curt. I'm not sure
of the date but probably around
August 10th
Ready for sub-floor
inspection
August 19th: Passed inspection, floor sheeting
in place
The girder
under the
new kitchen
goes . . .
. . . up
Ground floor framing starts
August 20th
Installing joists for
second floor